This Cottage we started about 12 days ago, and the following snapshots demonstrate the controlled speed we drive everyday, including Saturdays, and some Sunday. Foundation takes about 7 days.

Day 1 and 2 of the framing.

Day 3 and 4 of the framing.

Existing inspiration for the current Catskill Farms Cottage 23. Day 5.


Another picture of Day 5 framing. Dean the framer will be done tomorrow, paving the way for the roofer, the electrician, the plumbers, the heating guys and the siding guys. Keeping this pace will allow for a 3 to 4 month build time, getting someone into this cottage by Christmas.