November 30, 2023
All in a days work -
I do a lot in a day. Here’s some of it:
Sullivan County -
- Backfilled a new foundation in Narrowsburg, a house that quickly went into contract.


- Laid out 3 new homes on 3 new pieces of land in Narrowsburg I am purchasing. Marked driveways and house clearing locations, as well as dug deep pits for septic engineering.
- Checked up on 2 underground electric projects we have been waiting months for the poles to set. Poles set last week, this week we dug, now we pester NYSEG utility until we get electric.
- Continued with the fireplace and siding work at the Wanger residence in Forestburgh, as well as the rough mechanical plumbing work.

Ulster
- ¾ done with a ¼ mile long underground electric trench in Olivebridge. Every hurdle possible encountered - hard rock, lots of rain in an open trench. 3 days turned into 3 weeks. Ugh.
- Installed a kitchen at Farm 74. For Sale
- Finished the 2nd accessory building we are including in some of our homes. A 150 sq ft structure with big doors, windows, insulation, electric and heat.
- Continued framing a house at Lot 7, Ashokan Acres. Under contract.
- Siding, and rough electrical work at Lot 6, Ashokan Acres. Under contract.

Columbia
- Finishing up the Kaufman residence in record time.
Administrative -
- 9 employees, payroll, bills, mail, ordering, designing, warrantying.
- Couple of sales calls
- Couple of calls with attorneys, surveyors, accountants and what have you.
- Managing a rental portfolio of 6 homes.